Diameter: 300mm
Project Length: 1 day
Completed by: Kompozit’All
Initial Situation:
Brighton Town Hall is a Grade 1 Listed property. Many attempts had been made to install 300mm diameter Stainless Steel Flexible Liners all of which failed. During one attempt holes were excavated in the chimney to pull the steel liner through. Following this unsuccessful attempt, the chimney sealant failed to seal the holes.
Project Challenge:
Complete the lining of the chimney, whilst also sealing all the holes that had been created.
Liner Chosen:
FuranFlex 25 Black
Result:
It was recommended to line the chimney with FuranFlex 25 Black. This would ensure the chimney was lined with one piece lining with no joins and carrying a 25-Year Guarantee. A CCTV survey was carried out on the chimney to confirm dimensions and condition of the flue. The FuranFlex installation was carried out and finished on programme (within one day) allowing other trades to continue with the boiler installation works. The installation was then successfully smoke tested.
Completed by:
INSTALLER, KOMPOZIT’ALL