SE & U Duct Relining – FuranFlex Case Studies

Job type: SE & U Duct
Project Length: 1 day
Completed by: Kompozit’all UK

Initial Situation:
University College London’s Chemical duct from the chemical cabinet was leaking. The duct was located in a service riser with no access from the floors of the building.

Project Challenge:
To reline the duct without need to access ductwork through the building.

Liner Chosen:
FuranFlex 25 Black

Result:
The duct was successfully relined with FuranFlex Black. Access was only required at each end of the duct. The works were completed in 5 hours with minimal disruption to the building.

Completed by:
Kompozit’all UK

Make An Enquiry